First article inspection in accordance with MIL-B-18:
Visual and mechanical (external).
Battery voltage.
Vibration test.
Mechanical-shock test in accordance with MIL-STD-202, method 213, test condition I.
Insulation resistance test in accordance with MIL-STD-202, method 302, test condition B,
tolerance ±20 volts.
Capacity, D (without storage).
Jacket integrity test.
Conformance inspection in accordance with MIL-B-18:
Visual and mechanical (external).
Battery voltage.
Insulation resistance test in accordance with MIL-STD-202, method 302, test condition B,
tolerance ±20 volts.
Vibration test.
Mechanical-shock test in accordance with MIL-STD-202, method 213, test condition I.
Jacket integrity test.
Electrode leakage.
Capacity, D and T.
Method of examination and test:
Capacity tests: See requirements for capacity specified herein.
Storage:
Test
Period
D
18 months
T
90 days
Discharge:
The battery shall be discharged through 10 ohms for 4 hours, then on open circuit for
20 hours. This cycle shall be repeated 5 days per week continuously to a test-end
voltage of 3.6 volt.
Closed circuit voltage:
Use TS-183 ( )/U test per special marking or, with minimum permissible
voltage as specified for TS-183 ( )/U, use a load resistance value of 11.99
ohms.
Special marking on each unit package:
TO TEST THIS BATTERY WITH TS-183 ( )/U:
USE JACK NO.
MINIMUM PERMISSIBLE VOLTAGE
6
5.60
Unless expressly authorized, this test information shall
apply to Army and Air Force applications only.
Part or Identifying Number (PIN): BA-410/U, see 1.2 of MIL-B-18.
Reference documents. In addition to MIL-B-18, this document references the following: